Panama Canal Expansion Well on Track

After the arrival of the second set of rolling gates, the Panama Canal Expansion keeps moving forward reaching a new milestone at the Pacific side with the pouring of more than two million cubic meters of concrete.

“This is another milestone that shows the progress of various components of the Canal Expansion Project,” said the Administrator of the Panama Canal Authority, Jorge Luis Quijano.

The pouring mark of more than two million meters of concrete was reached this month in one of the monoliths that is on the west wall of the middle lock chamber.

In total, 4.3 million cubic meters of concrete is required to complete the construction of two lock complexes. To date, a total of 1.8 million cubic meters of concrete has been poured on the Atlantic side.

Panama Canal Expansion Well on Track1

The new lock complexes in the Pacific and Atlantic sides will feature three chambers, three water-saving basins per chamber, a lateral filling and emptying system, and rolling gates.

A total of 76.3 percent progress has been achieved under the Canal Expansion Program as of May 31, 2014.

Press Release, June 26, 2014

Share this article

Follow World Maritime News

In Depth>

Events>

<< Feb 2019 >>
MTWTFSS
28 29 30 31 1 2 3
4 5 6 7 8 9 10
11 12 13 14 15 16 17
18 19 20 21 22 23 24
25 26 27 28 1 2 3

GREENTECH IN SHIPPING GLOBAL FORUM

The mindset of sustainability and efficiency is the key to unlocking successful business…

read more >

LNG2019

LNG2019 features the largest number and highest level of LNG industry leaders.

read more >

Singapore Maritime Week (SMW) 2019

very year, SMW gathers the international maritime community for a week of flagship conferences…

read more >