Concordia Removal: 80 Pct of Sponson Installation Done

 Over 370 Titan Micoperi technicians are working restlessly on the installation of sponsons, prior to refloating phase of the Concordia wreck, the Parbuckling Project Team informed.

80 Pct of Sponson Installation Done

Currently, 14 sponsons have been installed on the starboard side of the Concordia and, if weather conditions will allow, today the last sponson will be positioned on this side (S1) to reach the total of 15.

Operations will then continue on the sea side, to install the last missing 4th sponson (11 had already been installed before the parbuckling).

The Italian Government has delayed the date of the final decision on refloating and removal of the Concordia wreck for June 26th so as to look into the plan’s details once more.

The additional time would be used for revision of risk assessments and proposed mitigation measures. The previous plans envisaged refloating of the hulk on July 20, followed by its towage  to Genoa, where the wreck would be dismantled. The delaying of the final decision might push the refloating schedule.

Press Release, June 20, 2014

 

Share this article

Follow World Maritime News

In Depth>

Events>

<< Dec 2019 >>
MTWTFSS
25 26 27 28 29 30 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Maritime Reconnaissance and Surveillance Technology

As varied threats in the Mediterranean Sea continue to proliferate, the need to advance…

read more >

2nd GREENTECH IN SHIPPING GLOBAL FORUM

Forum you will find out from the regulators, government bodies and major ports’ representatives what the near…

read more >

7th Annual Arctic Exchange

Every year the Exchange invites delegates from across the globe to come together to listen to key senior management teams…

read more >