‘Oleg Strashnov’ Installs Meerwind Topside

Seaway Heavy Lifting’s crane vessel “Oleg Strashnov” has completed the installation of the 3,300 mT transformer topside of the WindMW Meerwind project.

The installation took place at a water depth of 23 meters in the German Bight on 3rd April.

With the installation of the topside the wind farm is completed. The Meerwind offshore wind farm has a capacity of 288 MW and consists of 80 wind turbines of 3.6 MW each.

Seaway Heavy Lifting performed the Transport & Installation of transition pieces, the transformer topside as well as the jacket for WindMW.

The Meerwind project started for Seaway Heavy Lifting in September 2011 and the offshore installation part of the transition pieces and the jacket took place in the second quarter of 2013.

Seaway Heavy Lifting, April 11, 2014

Share this article

Follow World Maritime News

In Depth>

Events>

<< Mar 2020 >>
MTWTFSS
24 25 26 27 28 29 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31 1 2 3 4 5

Seawork 2020

Seawork is Europe’s leading commercial marine and workboat exhibition, providing businesses the opportunity…

read more >

Belgian Offshore Days 2020

During this event, a conference will be held with focus on “Increasing value by data driven innovation…

read more >

World Future Ports Summit 2020

This event will bring together ports and maritime shipping professionals from global leading companies and authorities to discuss recent digital technologies…

read more >

Europort Romania

Europort Romania is the premier maritime networking event of the Black Sea and will connect maritime technology and service suppliers with high level professionals from Romania and surrounding shipbuilding markets.

More info

read more >