First Jack-Up Vessel Built in Germany for Offshore Wind Farms Leaves Sietas Shipyard

It is a first in the German shipbuilding industry: The “Aeolus”, the first jack-up vessel for offshore wind farms designed and built in Germany, which was constructed at Sietas Shipyard for the prestigious Dutch marine engineering company Van Oord, has left the shipyard. Having passed through the Este barrage of Hamburg port, the jack-up vessel now travels along the river Elbe to Bremerhaven.

Berthold Brinkmann, administrator at Sietas Shipyard said, “I am proud of what the employees at Sietas shipyard have accomplished with this ship. They have always put in the maximum effort in the course of the insolvency process, and as a result a highly complex special-purpose vessel has been produced for demanding offshore wind farm projects. At the same time I would like to thank the company Van Oord and in particular Director, Mr Peter Bunschoten for their trust in Sietas shipyard with this order during the ongoing insolvency process. The vessel is proof of the efficiency and internationally competitive expertise in construction and building services at Sietas Shipyard. It is the first time a special-purpose ship such as this has been developed and built at a German shipyard. Sietas and Van Oord have reached a milestone in German shipbuilding today.”

Dr Tobias Brinkmann negotiated and finalised the new Van Oord construction contract during the Sietas insolvency process for the administrator along with Director Peter Bunschoten and Legal Counsel Ingrid Pieters, both from Van Oord. Sietas Shipyard then built the ship without any public funding or loans.

Design and building phases

Following the initial construction phase, the steel work for the hull was first completed on a building platform in the dock at Sietas Shipyard. The jack-up vessel was then removed from the platform so that it floated in the dock for final assembly. In recent months the deckhouse, containing the bridge, cabins for the crew and a kitchen, was erected, as well as four so-called jack-houses, each containing the hydraulics and the lifting system for the stilts on which the ship can be raised when at sea. In the last step, the crane was installed. It comes from the former Sietas subsidiary Neuenfelder Maschinenfabrik (NMF), now part of the TTS Group.

With commissioning, the construction of the ship has now been completed. The special dimensions of its four stilts, each 84 metres in length, and their “shoes” mean that they have to be fitted outside of the port of Hamburg.

During the construction period Sietas Shipyard also worked closely with the Ministry of Economic Affairs of the Free and Hanseatic City of Hamburg and Hamburg Port Authority (HPA), which kept the dock and access from the river Este to the river Elbe clear by dredging.

Sietas shipyard, February 18, 2014

Share this article

Follow World Maritime News

In Depth>

Events>

<< Feb 2018 >>
MTWTFSS
29 30 31 1 2 3 4
5 6 7 8 9 10 11
12 13 14 15 16 17 18
19 20 21 22 23 24 25
26 27 28 1 2 3 4

Shipping 360

This course is ideal for those who have recently joined the maritime sector and those who need to have a better understanding…

read more >

APM – ASIA PACIFIC MARITIME 2018

27 years in the making, APM is the premier shipbuilding & marine, workboat and offshore exhibition in Asia trusted by generations of industry professionals.

read more >

Shippax Ferry Conference 2018

The two-day onboard ferry conference was first organized in 2003 and grows ever more popular with some 400 delegates from over 40 ferry…

read more >

8th Dredging & Land Reclamation World Summit 2018

The 8th Dredging and Land Reclamation Summit 2018 will gather the decision makers from Authorities and Operators responsible for ports…

read more >