Indian Navy to Take Over Aircraft Carrier INS Vikramaditya in December

Aircraft carrier INS Vikramaditya (former Russian aircraft-carrying cruiser Admiral Gorshkov) will be delivered to Indian Navy on Dec 4, 2012, reports ITAR-TASS referring to a source in defense industry.

The carrier’s sea trials will start on May 29, and in accordance with the contract terms the ship will be handed over to India on December 4“, said the source.

As was reported earlier, sea trials of the carrier will take place in the Barents Sea within two or three weeks. Then will come 3-months of air wing tests.

The contract for modernization of aircraft-carrying cruiser Admiral Gorshkov (renamed into INS Vikramaditya) for Indian Navy was tied in 2004. It became the largest export contract in Russian-Indian military technical cooperation. Initially, modernization was evaluated as $616 mln, and the ship was planned to join Indian Navy in 2008. However, due to increased scope of works, the ship’s delivery date was postponed for 2012.

Shipbuilding Tribune Staff, March 7, 2012

Share this article

Follow World Maritime News

Posted on March 7, 2012

One thought on “Indian Navy to Take Over Aircraft Carrier INS Vikramaditya in December”

Comments are closed.

In Depth>

Events>

<< Feb 2017 >>
MTWTFSS
30 31 1 2 3 4 5
6 7 8 9 10 11 12
13 14 15 16 17 18 19
20 21 22 23 24 25 26
27 28 1 2 3 4 5

Seatrade Cruise Global

For more than 30 years, Seatrade Cruise Global has been the leading international exhibition and conference serving the cruise industry…

read more >

Focusing on Solutions

The maritime industry is experiencing the most aggressive regulatory change in history, with the adoption of a global sulphur cap of .5%…

read more >

European Shipping Week 2017

European Shipping Week is intended to be a platform where policy-makers from the main EU institutions will meet and engage with European…

read more >

SNS2017 – The Southern North Sea Conference & Exhibition

EEEGR’s flagship Southern North Sea conference is the most important event for the energy sector in the East of England. Taking place over two days at the Norfolk Showground Arena in Norwich, SNS2017 will be the largest conference and exhibition EEEGR has ever delivered attracting upwards of 700 delegates from across the industry and supply chain.

Key industry players will gather at this event to discuss and debate issues, network to make new business contacts and re-establish relationships with existing clients.

Why should you attend?

  • Generate fresh leads and meet new contacts in a time and cost-efficient way.
  • Showcase your expertise and share your insights to impress your clients.
  • Meet senior-level delegates looking to learn and seek out new partners.
  • Account manage and liaise with your current clients attending – or bring them along yourself as an account management tool.
  • Months of intensive marketing and advertising to relevant markets ensuring a high level of attendance.
  • Numerous on the day and follow up advertising opportunities available to enhance your positioning.
  • Stay one step ahead of your competitors by being seen and visibly present at the event.
  • Develop your brand and status within industry by being billed as an event sponsor.

SNS2017 – 2 March

Day two of the conference is dedicated to ScottishPower Renewables Supply Chain Event for the East Anglia ONE Wind Farm Project.

ScottishPower Renewables is in the process of finalising its major contracts for the East Anglia One project, and is delighted to announce that these contractors will be attending the ScottishPower Renewables Supply Chain Event at the Norfolk Showground Arena on 2 March 2017.

Occupying the second day of EEEGR’s SNS2017 Conference and Exhibition, the ScottishPower Renewables Supply Chain Event will allow their contractors to engage with businesses and stakeholders in the East of England and further afield as quickly as possible to outline the skills they require and the business opportunities to be created by the project.

Information will be provided on the current status of the project by ScottishPower Renewables Managing Director, Jonathan Cole, and East Anglia One Project Director, Charlie Jordan. There’ll also be information on the scope of works to be carried out, explanations of how to get involved and the opportunity to meet representatives from Seaway Heavy Lifting, Navantia, Lamprell, Harland & Wolff, Roadbridge, Van Oord, Prysmian, VBMS, Nexans, DeepOcean, Peel Ports Great Yarmouth, Siemens and ABPorts.

Up to seven additional suppliers will also be attending, to be confirmed shortly. Opportunities will range from civil and electrical contractors, vessel and ports support, to technicians and logistics.

ScottishPower Renewables is starting construction this year, with the first turbines to be installed by 2019 and the project fully operational during 2020.

Full-access pass holders will be able to take full advantage of the presentations whilst there are also free exhibition-only passes which will give holders the opportunity to network with representatives from these suppliers at their stands. Delegates MUST register prior to the event to be allowed admission. Upgrades of exhibition-only passes may be permissible on payment of the appropriate fee.

More info

read more >